Vague epics produce vague estimates. Break the project until each leaf task is something one person can finish in about a day or two of focused work. If a task is still "implement notifications," keep splitting: schema, producer, consumer, retries, metrics, feature flag, docs.

Concept

A spike is a time-boxed investigation (half a day to two days) whose deliverable is knowledge, not production code. Schedule spikes before you estimate the dependent work.

Estimating "migrate the billing pipeline" without a spike is fiction.

Walking through a breakdown

A PM asks: "Can we ship shared report folders by the 28th?" Today is the 4th.

Spike (day 1–2). Permissions model already has groups; folders do not. ACL inheritance is unclear. Spike result: reuse group ACLs, add folder_id nullable on reports, no new auth service. Confidence rises.

Then the leaves (raw eng-days):

TaskDaysNotes
Schema + migration1Expand-contract
Folder CRUD API1.5
ACL inheritance rules2Highest risk remaining
UI list/move2Junior can take with pairing
Empty-state + errors0.5
Metrics + flag + runbook1
Tests + review buffer2
Raw sum10

Every row is ≤2 days. The ACL line is still the wild card — that is why it got a spike first, and why it will get a larger padding factor next.

Tip

Write spike outcomes down: what you tried, what you learned, recommended path. That note feeds the design doc and stops the next person from redoing the same dig.

Common mistakes

  • Leaving a task at "implement notifications." That is still an epic.
  • Estimating the unknown work before the spike.
  • Letting a junior's optimism set the team date without a senior pass on the risky tasks.

Check yourself

The ticket says "implement notifications." What do you do before quoting a date?

Split it into schema, producer, consumer, retries, metrics, flag and docs — and spike anything you have not seen.

A spike shows you cannot reuse the existing outbox. What happens to the estimate?

The dependent work changes. Re-estimate now; do not keep the pre-spike number.

Key takeaways

  • Break work to about one or two focused days per leaf.
  • Spike unknowns before you pretend to know their cost.
  • Write the spike down so it feeds the design and the next person.
  • Risky leaves stay visible in the table. Do not bury them in a lump.