Work breakdown and spikes
Split work until each leaf is about one or two focused days. Time-box unknowns as spikes before you pretend to know their cost.
Vague epics produce vague estimates. Break the project until each leaf task is something one person can finish in about a day or two of focused work. If a task is still "implement notifications," keep splitting: schema, producer, consumer, retries, metrics, feature flag, docs.
Concept
A spike is a time-boxed investigation (half a day to two days) whose deliverable is knowledge, not production code. Schedule spikes before you estimate the dependent work.
Estimating "migrate the billing pipeline" without a spike is fiction.
Walking through a breakdown
A PM asks: "Can we ship shared report folders by the 28th?" Today is the 4th.
Spike (day 1–2). Permissions model already has groups; folders do not. ACL inheritance is unclear. Spike result: reuse group ACLs, add folder_id nullable on reports, no new auth service. Confidence rises.
Then the leaves (raw eng-days):
| Task | Days | Notes |
|---|---|---|
| Schema + migration | 1 | Expand-contract |
| Folder CRUD API | 1.5 | |
| ACL inheritance rules | 2 | Highest risk remaining |
| UI list/move | 2 | Junior can take with pairing |
| Empty-state + errors | 0.5 | |
| Metrics + flag + runbook | 1 | |
| Tests + review buffer | 2 | |
| Raw sum | 10 |
Every row is ≤2 days. The ACL line is still the wild card — that is why it got a spike first, and why it will get a larger padding factor next.
Tip
Write spike outcomes down: what you tried, what you learned, recommended path. That note feeds the design doc and stops the next person from redoing the same dig.
Common mistakes
- Leaving a task at "implement notifications." That is still an epic.
- Estimating the unknown work before the spike.
- Letting a junior's optimism set the team date without a senior pass on the risky tasks.
Check yourself
The ticket says "implement notifications." What do you do before quoting a date?
Split it into schema, producer, consumer, retries, metrics, flag and docs — and spike anything you have not seen.
A spike shows you cannot reuse the existing outbox. What happens to the estimate?
The dependent work changes. Re-estimate now; do not keep the pre-spike number.
Key takeaways
- Break work to about one or two focused days per leaf.
- Spike unknowns before you pretend to know their cost.
- Write the spike down so it feeds the design and the next person.
- Risky leaves stay visible in the table. Do not bury them in a lump.
Further learning
Next, turn the raw sum into a range: estimate ranges and padding.
Related
Estimation and planning
Breaking work into small tasks, estimating with ranges, de-risking early, and communicating slips before they become surprises.
Estimate vs commitment
An estimate is a range under uncertainty. A commitment is a date you agree to hit, usually by cutting scope. Do not give one when asked for the other.